A resource consent is processed under the Resource Management Act and district or regional plan and covers the land use, subdivision or discharge parts of the development. A building consent is prepared and processed under the Building Act and covers the building structure itself. Building consents will usually follow the resource consent stage and building works cannot commence until all required resource cosents are obtained.